Prepare for the CPIM Exam with our comprehensive quiz. Hone your skills with expertly crafted questions that simulate the exam environment. Get the confidence you need to ace your certification test and propel your career in supply chain management!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the relationship between the master production schedule and the production plan?

  1. The MPS provides input to the production plan

  2. The production plan is set based on the MPS

  3. They are developed independently of each other

  4. Both are determined by market demand forecasts

The correct answer is: The production plan is set based on the MPS

The master production schedule (MPS) and the production plan have a crucial interrelationship in the context of production and operations management. The correct choice emphasizes that the production plan is influenced by the MPS, reflecting the need for a cohesive strategy in meeting production goals. The production plan typically outlines the overall strategy and resource allocation needed to meet anticipated demand over a specific time horizon. In contrast, the master production schedule breaks down this plan into specific manufacturing activities, detailing what products will be produced, in what quantities, and when. It essentially operationalizes the broader production plan. Choosing this option illustrates the flow of information from the MPS to the production plan, highlighting how the detailed scheduling provided by the MPS helps to refine and implement the broader strategies defined in the production plan. This is vital because the MPS is informed by actual customer orders and demand forecasts, thus ensuring that the production plan remains aligned with real-time market conditions. This alignment helps organizations optimize their production and resource utilization effectively.