What characterizes finite forward scheduling?

  1. Building schedules based on estimated completion dates

  2. Proceeding sequentially while observing capacity limits

  3. Starting from the last operation to the first

  4. Overlapping multiple operations without constraints

The correct answer is: Proceeding sequentially while observing capacity limits

Finite forward scheduling is characterized by proceeding sequentially while observing capacity limits. This approach involves planning production activities by starting with the first operation and moving to the last while considering the machine and labor capacities available. By adhering to these constraints, finite forward scheduling helps prevent overloading resources, ensuring that the production process remains within achievable limits. This method is essential in environments where resource availability is a critical factor, as it allows for a realistic and achievable schedule that maximizes efficiency without exceeding the capacities of the system. By focusing on capacity constraints, companies using this scheduling technique can better align their operations with demand and resource availability. In contrast, building schedules based on estimated completion dates can lead to inaccuracies and misalignments in the actual production flow, while starting from the last operation to the first is characteristic of backward scheduling. Overlapping multiple operations without constraints may lead to resource conflicts and inefficiencies, making it less viable in resource-limited environments.